Since 2009, the province of Ontario, Canada, has had an
incentive
program that pays homeowners, schools, companies, and other
organizations for solar power that they generate. This power is
fed to the electrical grid. The program is divided into two:
microFIT and FIT.
The microFIT is for homeowners, companies,
schools, cooperatives and other organizations who own the system
and produce 10kW or less.
The FIT is also for owners of the systems
but produce more than 10kW.
FIT stands for Feed-in Tariff. Each program has different rules.
The contract period is 20 years.
Different amounts are paid depending on the system size and type:
Pays
Size
Type
Program
$0.549
10kW or smaller
roof mounted
microFIT
$0.445
10kW or smaller
ground mounted
microFIT
$0.548
10 to 100kW
roof mounted
FIT
$0.539
100 to 500kW
roof mounted
FIT
$0.487
greater than 500kW
roof mounted
FIT
$0.388
10 to 500kW
ground mounted
FIT
$0.350
500kW to 5MW
ground mounted
FIT
$0.347
greater than 5MW
ground mounted
FIT
In Ontario, Canada the average consumer can pay around $0.20 per kWh for
electricity (total bill amount/kWh used) so this is a substantial
incentive.
The high cost of solar panels still plays a big part in the decision
as to whether or not to go with this approach. The following is a
quick back of the envelope calculation to illustrate this. As the
table shows, a 2.3kW PV system costs around $17,000 (rounded
up to the nearest $1000).
Cost
Item
$7,980
10 solar panels x 230W per panel at $798 each
$500
racking/frame
$2,404
grid-tie inverter
$450
cables to run power from the panels to the inverter
$200
other parts/hardware
$2050
various fees (inspection fee, connection cost, building permit, meter)
$3000
installation/labour
$16,584
Total
Assuming an average of 4 hours of sunlight per day, it would
generate 4 x 2.3kW per day, which is 9.2kW. 9.2kW per day x 365
days in a year gives 3,358kW per year of generated power. At
$0.549 per kW x 3,358kW, that's $1,844 per year of income. Given the
initial cost of $17,000 divided by $1,844 per year, it would
take just over 9 years to cover the initial costs and start making a
profit for the remaining 11 years of the 20 year contract.
The panels typically have a 25 year warranty and the inverter
a 10 year warranty. The only part likely to be replaced during the
contract is the inverter since there are some electronic components
in it that can wear out.
Annual costs will vary. For example, there may be a small account
charge with the local distribution company (power company). Also,
the system will add to the value of the property, possibly increasing
the property taxes. There is also the consideration of getting
insurance. The income from this program is taxable income.
However, if grants or subsidies are available then they can reduce
the initial cost, giving an earlier payback. Another approach is
to have a leasing company purchase the solar panels and other
hardware and then lease it to you, causing you to begin making
money much sooner, though since you wouldn't own the hardware,
you will always have the cost of paying the leasing company.
Domestic content requirements for microFIT
One interesting feature of the Ontario program is the required
domestic content. The installation must have 60% domestic content.
The 60% formula basically means all the mounting structure,
the hardware, the wiring, the solar panels and the inverter must be
made in Ontario, and the labour must be from Ontario.
The purpose of the domestic content requirements is to help
grow the green industry in Ontario. Inverter companies
like SMA Solar Technology AG, and solar panel manufacturers such
as Canadian Solar and Opsun Panels are working on
opening plants in Ontario.
News
Government
March 22, 2012 - The results of the
Two-Year FIT Review have been announced. The main highlights are:
The payment amounts have been significantly lowered, reflecting
the lowering prices for solar panels over the years. The new
amounts are in the table at the top of this page. As an example, a
roof mounted microFIT (<=10kW) used to pay $0.802 per kWh but will
now pay $0.549 per kWh. But as you can see from the above back of
the envelope calculation, you can still get a payback of under 10
years for the 20 year contract.
It's been recommended not to go ahead with the CFIT (Commercial FIT)
program. This program has long been under consideration for
allowing companies to "rent" people's rooftops or property for
installing systems on.
Much has been recommended for encouraging greater community and
Aboriginal participation.
July 7, 2011 - The Ontario provincial government released a
Progress Report that included the progress regarding clean energy
and infrastructure. Highlights on the electricity side are:
More than 2,000 megawatts of new electricity supply from
sustainable, renewable sources have been brought online -
enough to power nearly 900,000 homes,
13,000 clean energy jobs have been created.
Reduced coal usage for 2011 by 90% from 2003 and are on
track to eliminate all coal altogether by 2014.
Went from 10 wind turbines in 2003 to 900 in 2011 and
now have the capacity to power more than 350,000 homes.
Have more than 200 megawatts for solar capacity online,
enough to power more than 30,000 homes.
Signed or offered contracts for more than 21,000 small, medium
and large clean energy projects and about $13 million in private
sector investment, including investment in manufacturing.
Industry growth
The following is a collection of announcements of plants either planned
or in production as a direct result of this Feed-in Tariff program.
June 2, 2011
Hanwha SolarOne has entered into a supply agreement with Photowatt
Ontario, Inc.,(PWO) a wholly owned subsidiary of ATS Automation Tooling
Systems, where Photowatt will produce Hanwha SolarOne PV modules to serve
the Ontario marketplace.
United Solar... announced that it will establish a manufacturing
facility in Ontario, Canada, that will be operational by August 2011.
The 7,000 square meter facility, located at 6135 Morton Industrial
Parkway in LaSalle, Ontario, is under lease to the company for 10
years, and will result in the hiring of up to 80 people.
February 1, 2011
Celestica Inc, a contract electronics maker, is expanding
solar-equipment manufacturing to serve renewable energy
developers seeking lucrative contracts being offered by the Canadian
province of Ontario.
December 6, 2010
SunEdison announced today that its affiliate, MEMC Singapore, is
partnering with Flextronics to produce solar photovoltaic panels at
Flextronics' facility in Newmarket, Ontario. Located in York Region,
production of the solar panels is expected to result in more than 100 new
jobs for the province.
November 25, 2010
ATS Photowatt officially opened its Photowatt Ontario Green
Wing production facility.
Suntech Power and Calisolar Inc., a privately held, vertically
integrated manufacturer of solar silicon, wafers and cells have signed
a Letter of Intent to construct a solar silicon manufacturing facility
in Ontario Canada.
October 4, 2010
Mecasolar has opened a new
manufacturing facility in the Canadian city of Wallaceburg (Ontario),
adding to its existing factories in California, Greece and Spain.
August 12, 2010
Canadian Solar will establish a new solar module manufacturing
facility in Ontario. The facility, located at 545 Speedvale Avenue,
West in Guelph, Ontario, Canada, is expected to be ready to commence
production early next year, and will be one of the largest solar
panel module manufacturing plants in North America.
August 2010
Samco Solar, formerly just an aut parts manufacturer, opened
a plant in Scarborough, Ontario, to produce solar mounting systems
resulting in 15 to 18 fulltime positions.
May 10, 2010
With an announcement May 7, the community [Sault Ste. Marie, Ontario]
is entering into a new phase in the green sector.
Heliene Canada
is constructing a solar panel
manufacturing facility on Second Line, which will employ up to 36
people.
March 9, 2010
SMA Solar Technology AG is to strengthen its presence in North
America with the foundation of a subsidiary in Canada.
March 1, 2010
Schletter GmbH announced today that it will begin office operations
of its Canadian subsidiary company, Schletter Canada, Inc., in
April. By May, Schletter Canada's manufacturing and distribution
facility will be fully operational for order fulfillment,
manufacturing, and distribution.